Commercial Stripout – Chelsea hub 2 Cobham
Description of Activity
- TROJAN ARE TASKED WITH THE STRIP-OUT OF THE CURRENT CHANGING ROOMS AND WASH AREA READY FOR REDEVELOPMENT
- ATTEND SITE SECURITY AND RECEIVE PASS AND PERMISSION-TO WORK
- ATTEND SITE SAFETY INDUCTION FROM PRINCIPLE CONTRACTOR
- INTEGRATE INFORMATION RECEIVED INTO TROJAN SITE SAFETY INDUCTION
- RECEIVE FROM P/C ALL POWER AND SERVICES ISOLATION’S
- USING VARIOUS HAND AND BATTERY OPERATED HAND TOOLS
- WORKING AT ALL TIMES IN A SAFETY CONTROLLED AND MINDFUL MANNER TO REDUCE AND OR ELIMINATE RISK AND IDENTIFY HAZARDS
- REMOVE ALL LAY IN GRID SYSTEM CEILINGS IN THE WORK AREAS
- REMOVE SLOWLY AND CAREFULLY THE EXISTING LOCKERS AND RELOCATE TO AGREED AREA
- STRIP-OUT ALL SANITARY WEAR
- STRIP-OUT AND REMOVE ALL DOORS AND FRAMES
- STRIP UP ALL VINYL FLOORING IN THE DESIGNATED AREAS
- STRIP UP AND INVESTIGATE THE MAKE UP OF THE FLOORING TO THE TOILET AND CHANGING ROOM AREAS
- WORKING FROM THE TOP STRIP-OUT AND DISMANTLE THE EXISTING PARTITION WALL 92m2
- MOVE ALL WASTE TO A SITED SKIP
- LEAVE SITE CLEAN TIDY AND SWEPT THROUGHLEAVE SITE CLEAN TIDY AND SWEPT THROUGH